Changed Design Intent
By Bob Baker
It is important that building use and HVAC system
design be carefully coordinated. I recently encountered
an interesting project that illustrates this point
dramatically.
In this case, a detached medical office and surgery
center open for less than three months, the Physician
was examining a patient and water started dripping
on them. This happened because significant quantities
of moisture are condensing out of the air in the attic
on various surfaces located above the suspended ceiling
throughout the facility.
Facility description
This is a free-standing medical practice facility
located in Florida. It is concrete block/stucco construction
with wood frame tile roof. The total of area of about
6,000 sq ft is separated by a fire rated wall into
two sections of roughly equal size. The first is the
administrative/waiting area and the second is an outpatient
surgical facility. Each side is served by independent
HVAC and exhaust systems. Both have 5 ton heat pumps
with a outside air pre-processing unit supplying 735
CFM of dry outside air to the surgery center.
The facility was designed with perforated soffits
and roof vents with insulation above the suspended
ceiling. During construction, the design was changed
to conform to health facility design code that requires
the air-handlers and air ducts to be within the conditioned
space. The soffits were removed and replaced with
solid panels and the roof vents were closed up. Insulation
was removed from above the ceiling and installed between
the rafters.
Walkthrough Inspection
An inspection of the attic spaces revealed the following:
A. Water stains were observed at several locations
throughout the facility. B. The overflow pans below
both AHU1 and AHU2 contained water. C. Moisture was
noted at the following locations: AHU tops and bottoms,
register boots, several of the connection points between
flexible duct sections and the duct board plenums.
D. Relative humidity varied from 68-72% and dew point
ranged from 72-76 degrees F. The thermostat set points
in the below ceiling space were near the Dew Points
recorded in the above ceiling spaces. As a result,
un-insulated surfaces that interface with both spaces
were condensing surfaces on which a moisture film
was accumulating. Both RH readings were above the
level where EPA, ASHRAE and others recognize that
active mold growth is highly probable. E. A gray fibrous
buildup later confirmed to be fungal growth was observed
on several of the wooden structural members in the
attic.
What happened?
The difficulties being experienced in this facility
rise from two general causes: a) The conversion of
the building design from a cross ventilated attic
to a sealed attic design. b) Negative pressurization
of the building envelope relative to the exterior.
Each of these is discussed more fully below:
Design intent change - Under the initial design concept,
the ceiling of the facility served as a combined thermal,
air and vapor barrier between the work spaces and
the attic area. Although, a suspended ceiling has
poor thermal, air and vapor barrier properties, insulation
bats with a vapor retarder facing to the conditioned
space dramatically improve the barrier performance
of the suspended ceiling system. The combined materials
provide enough thermal, air-flow and vapor movement
resistance that the area above the ceiling and that
below the ceiling are effectively isolated from each
other; a common situation in light commercial construction.
Under this arrangement, the below ceiling structure
is built "tight" to limit infiltration of air, moisture
and heat in hot and humid climates. The above ceiling
space is built "loose" and incorporates vents added
to encourage the free exchange of air with the exterior
of the building. The roof design serves as a barrier
to liquid (rain) while permitting the passage of air,
water vapor and to some extent, heat. When the use
of the building was changed (surgery center added),
codes required that all HVAC airside components be
contained within the conditioned space. To do this,
the contractor moved the insulation and vapor retarder
from the top of the ceiling to a position between
the rafters. In addition, the roof vents were sealed
and the perforated soffits replaced with solid soffits
panels. Although this might have decreased free cross
ventilation of the attic space considerably, it did
not bring that space to the level of "tightness" of
the below ceiling space. Thus the above ceiling space
tended to seek balance with the exterior psychometric
conditions (temperature, moisture content and dew
point). Although, the ceiling is no longer an effective
thermal, air movement and vapor barrier, it retains
enough retarding properties to maintain a significant
differential between the psychometric conditions above
and below the ceiling. Thus, the ceiling and other
structural separation components serve as a thermal
bridge and "mini-environments" are set up where dew
point is reached and water condenses out of the air.
Building Pressurization - It is common (and preferred)
design practice in buildings in hot and humid climates
like Florida to maintain building pressurization positive
to the exterior. This is done by bringing in more
outside air than you exhaust. Naturally, it must be
pre-conditioned by cleaning, cooling or heating and
removing excess moisture. Under this situation, conditioned
air pushes against the building envelope and holds
out air with high moisture content and/or particulate
contamination. If the building becomes negatively
pressurized, there is a risk that both moisture and
contamination will be pulled into the building through
unsealed penetrations and other entry points. The
incompletely sealed soffits provided significant opportunity
for infiltration of both moist air and contamination.
Healthcare regulations require, in order to promote
good infection control, that an exhaust system is
installed in such a facility to move air toward less
clean areas (restrooms, soiled utility, closets) and
away from clean areas. It is essential that this system
operate continuously when ever the building is in
use. The system in this building creates a combined
outflow of air totaling 775 CFM (cubic feet per minute).
This outflow must be overcome by outside air brought
in by the HVAC systems or the building will "go negative"
leading to infiltration of unconditioned air. Figure
1 is the building pressurization under various states
of system operation.
Figure 1:
| System STATE |
STATUS |
FLOW (CFM) |
| Neither AHU running |
NEG |
775 |
| AHU 1 only |
NEG |
585 |
| AHU 2 only |
NEG |
40 |
| Both running |
POS |
150 |
Under all conditions except when both systems are
running, the building interior is negatively pressurized
and there is risk of moisture and contamination being
pulled through the building envelope. This risk is
especially critical due to the current loose nature
of the soffit seal. The result is that the above ceiling
area has a ready supply of un-conditioned outside
air with high moisture content virtually all of the
time. This led to the massive moisture condensation
that was taking place.
Conclusion Both building construction and HVAC system
design and operation must be closely matched to the
needs and use of the space within the building or
indoor conditions will not be satisfactory. As this
article reveals, any change in space use must involve
a complete re-evaluation of both building and mechanical
system design to assure that the new use will be properly
supported. In a later article, we will discuss what
was done to bring this building to a satisfactory
condition and how successful that was.
Bob Baker is a member of IAQA, ASHRAE, CSPA and
Chairman and CEO of BBJ Environmental Solutions, Inc.,
"The Standard of Care for Indoor Air". BBJ has offices
in Tampa and Hong Kong and Mr. Baker follows indoor
air quality developments throughout the world. For
additional information, Mr. Baker can be reached at
(800) 889-2251 or through the company web site at
www.bbjenviro.com.
|