Changed Design Intent; Fixing
the Mess
By Bob Baker
In an earlier article, we described a new medical
office where the moisture level in the attic space
was so high that water was condensing on ceiling panels
and light fixtures and dripping on the Physician and
his patients. This resulted from a building design
change decision during construction that was incompletely
implemented.
We made two types of recommendations. Several were
"musts" because the building operation would continue
to fail occupant expatiations unless these were completed.
The rest were highly recommended for long term owner
satisfaction.
Must - These changes were required to conform to
current codes or natural law in order for the building
to perform in line with the planned use.
- Seal the roof assembly to the same level as the
below ceiling building envelope. This primarily
consists of minimizing heat, air and vapor movement
through openings in the soffit assembly. One possibility
is to remove the soffit panels, construct a sealed
barrier system above them and then replace the panels.
Another possibility might be to secure some gasket
or other sealing system that will make the current
soffits effective air-flow barriers. Whichever choice
is made, insulation with a vapor barrier facing
toward the interior space must be installed on top
of either the new structure or the soffit panels.
- Maintain building pressurization as positive regardless
of status (on cycle or off cycle) of the two air
handlers. Although this could be done by setting
the fan controls to continuous operation we noted
that option should not be considered under any condition
as operation of the fans without removing moisture
from outside air will make the current moisture
problem even worse. We suggested several options
for doing this without risk of increasing moisture
levels. We referred them to the design engineer
who completed the design of the current system for
his advice on which strategy to follow:
- Minimal option - An economizer type control
could be installed on the Pre treatment unit
so the fan would run at all times, and the compressor
would cycle as needed to maintain correct psychometric
conditions (ASHRAE Standards for energy and
comfort). This would take advantage of free
cooling when outside conditions allow.
- We also suggested several sources for ducted
dehumidifiers for residential/light commercial
use and suggested one of these could be installed
on the outside air input to AHU #1 and the controls
set to provide full time fan operation with
cycling of the refrigeration system as needed
to maintain acceptable psychometric conditions
in the outside air supply. Implementing both
of the above would provide slight positive pressurization
at minimal cost. It still would not be optimal
but would improve considerably on the current
situation.
- Second option - An enthalpy energy recovery
unit could be installed on the exhaust system
so as to remove heat and moisture from the outside
air supply and eject it to the exhaust stream
then furnish the processed outside air to the
conditioned space. The unit would have to be
sized to assure a net positive pressure to the
building. Under this option, the operation of
the current units could remain unchanged if
a recovery unit of sufficient size were installed
and could be made to provide adequate conditioned
outside air.
- Other options could also be considered including
a redesign of the entire HVAC system. Whatever
solution is chosen, the Florida Healthcare Facility
Design standards would have to be consulted
to assure that the resulting system meets regulations
for total supply air and outside air for the
surgery space.
- Finally we noted that the pre-treatment air handler
condensate line did not have a trap and one must
be installed.
Highly Recommended - These modifications/activities
are required for the facility to perform in the manner
expressed by the owner as desired, to prevent deterioration
of the building asset and facilitate maintenance.
- HEPA Vacuum all surfaces in the attic areas to
remove any settled spores present followed by fogging
of all areas with a growth inhibitor registered
by the US EPA for control of fungal growth (BBJ
Microbiocide for floors and walls or equivalent).
Although eliminating the excess moisture in the
attic space will probably stop the growth that was
starting to form, it is good practice to remove
what is existing and the inhibitor acts as an insurance
policy against regrowth.
- Rework all filter racks so that they meet the
guidelines contained in the National Air Filtration
Association IOM (Instillation Operation and Maintenance)
Manual. This includes providing gaskets and fillers
as needed to eliminate existing filter bypass (currently
estimated to be in excess of 15%) and providing
convenient change access to the final filter on
the system serving the surgery area plus installing
a differential pressure gauge to monitor the condition
of that filter (the gauge should be calibrated to
indicate the pressure maximum pressure drop recommended
by the media manufacturer prior to change out. The
existing filter installation was far below standard
and, although not part of the immediate complaint,
would eventually result in unsatisfactory operation.
- Replace the filter rack on the Carrier system
with a rack capable of supporting a higher efficiency
media. (MERV 6 minimum) MERV 6 is the minimum considered
adequate under current ASHRAE and other guidelines
for commercial buildings. For this type of facility,
MERV 11 would be preferable.
- Rework all fiberglass duct board plenums so they
meet the NAIMA Fibrous Glass Duct Construction Standard
using pressure sensitive tape (or fiberglass tape)
and mastic rated for UL 181A.
- Rework all flexible duct connections (including
those to register boots) so they conform to the
Air Diffusion Council Flexible Duct Performance
and Instillation Standards (Alternate Method 4.6)
using clamps and mastic that conform to UL 181B.
There were many air leaks throughout the duct system
that were both wasting energy and promoting moisture
condensation.
- Remove air handler internal insulation that has
become wet and replace with new insulation. Inspect
balance of HVAC system interior as indicated in
NADCA Standard ACR 2005 and clean or repair to that
standard as needed. It was incredible how soiled
the system was for a building that had been in operation
for only three months. We speculated that the system
had been operated during construction without filters
in place and not cleaned before the building was
occupied.
- Have Insulation Contractor reinstall insulation
between rafters using retaining netting so the insulation
will form a uniform thermal, air and vapor barrier.
We also considered that the owner consider one of
the new spray insulation systems as these would
be less likely to be dislodged than the bats and
provide a more effective air and vapor barrier.
What Happened?
When we last checked, some of the recommendations
had been implemented. The insulation had been reinstalled,
The duct system had been sealed according to current
industry standards and the existing mold had been
removed. The sealing of the soffit space was to be
completed the next week.
The HVAC contractor initially resisted any additions
to the system insisting that control modifications
(adding a humidistat) would handle the problem. The
day after the control modifications were completed,
water dripped on the Physician and now a heat/moisture
recovery system is on order.
Bob Baker is a member of IAQA, ASHRAE, CSPA and
Chairman and CEO of BBJ Environmental Solutions, Inc.,
"The Standard of Care for Indoor Air". BBJ has offices
in Tampa and Hong Kong and Mr. Baker follows indoor
air quality developments throughout the world. For
additional information, Mr. Baker can be reached at
(800) 889-2251 or through the company web site at
www.bbjenviro.com.
|